Chicago · building permits · month 2023-03
How many EV charging permits did Chicago issue in March 2023?
8. That is every matching building permit the City issued from 2023-03-01 to 2023-03-31, counted in the City’s own dataset ydr8-5enu and re-read hourly. Filter: Any permit whose work description mentions an electric vehicle, EV charging, or EVSE. The City has no dedicated EV permit type, so all three spellings are matched. 456 in the year to 2026-07-01.
EV charging permits issued in March 2023
8
Combined reported cost
$23,944
where the permit reports one
Permits reporting a cost
8
Largest single permit
$5,852
highest reported cost this month
Window 2023-03-01 to 2023-03-31 · measured 2026-07-31 · City of Chicago dataset ydr8-5enu
| Issued | Address | Permit type | Reported cost | Source |
|---|---|---|---|---|
| 2023-03-09 | 313 S RACINE AVE | PERMIT – EXPRESS PERMIT PROGRAM | $5,852 | B101008187 |
| 2023-03-13 | 1706 N MOZART ST | PERMIT – EXPRESS PERMIT PROGRAM | $4,600 | B101008720 |
| 2023-03-30 | 1201 W ADAMS ST | PERMIT – EXPRESS PERMIT PROGRAM | $3,000 | B101011094 |
| 2023-03-10 | 5242 N MARMORA AVE | PERMIT – EXPRESS PERMIT PROGRAM | $2,800 | B101008456 |
| 2023-03-23 | 4743 W WAVELAND AVE | PERMIT – EXPRESS PERMIT PROGRAM | $2,500 | B101010178 |
| 2023-03-09 | 1230 W HOOD AVE | PERMIT – EXPRESS PERMIT PROGRAM | $1,850 | B101008230 |
| 2023-03-01 | 1509 W ALTGELD ST | PERMIT – EXPRESS PERMIT PROGRAM | $1,742 | B101006885 |
| 2023-03-25 | 7086 N MCALPIN AVE | PERMIT – EXPRESS PERMIT PROGRAM | $1,600 | B101010454 |
March 2023 · week by week
Each week below holds every matching permit for its seven days, not just the largest. ISO weeks, so the first and last may reach a few days outside March 2023.
March 2023 · other trades
Permit Signal